Thursday, 18 April 2013

The internal plot drainage, services and substructure block work is now complete, which means the beam & block floor can be installed. Also the foundations for the kerbs have been formed and the road is being trimmed and levelled ready to receive tarmac base course.


Beam and block floor is now installed, which only took 2 days to complete.

Tuesday, 2 April 2013

With the foundations now fully cured, the substructure blockwork has come along very quickly in a short space of time, which has allowed the groundworkers to install the foul drainage under the building.