It's been another action packed week on site this week, we have had trades
starting and trades finishing. The partitions walls
are complete now so the plasterer has been following them and plastering the
flats. The flats are now complete so that just leaves the communal areas to
finish plastering. The brickwork is
getting ever closer to its summit. The joinery is
continuing to the first floor flats, the decorator has been on site mist coating
the flats on all floors and the staircase walls and ceiling making it look a lot
brighter. Meanwhile on the top
floor the electricians have been carrying out their second fix works to the
flats.
Friday, 27 September 2013
Friday, 6 September 2013
Work to the superstructure has moved swiftly on this week until the weather took a turn for the worse on Friday. Internally the plastering is now complete on the first and second floors, the kitchen for the second floor were delivered earlier in the week so the joiner has started to fit these along with his second fixing of the flats to the second floor. The plumbers have started back on site with their second fix to the flats on the second floor also. The decorator was on site early in the week to mist coat the top floor to enable the M&E to start their second fix.