Work to the superstructure has moved swiftly on this week until the weather took a turn for the worse on Friday. Internally the plastering is now complete on the first and second floors, the kitchen for the second floor were delivered earlier in the week so the joiner has started to fit these along with his second fixing of the flats to the second floor. The plumbers have started back on site with their second fix to the flats on the second floor also. The decorator was on site early in the week to mist coat the top floor to enable the M&E to start their second fix.