Well what another glorious week we have had with fantastic sunshine all week, we have been getting sun cream and water delivered by the lorry load its been that hot!
Works on site have progressed well this week, the partition walls to the first and second floors have been erected, and plaster board has been fixed to one side of the walls so the services can be installed. The plumbers started on site at the beginning of the week, and by the close of play Friday the four flats to the second floor were 1st fixed.
Meanwhile the taping and jointing to the ground floor was carried out in readiness for the timber service batten being fixed to enable the partition walls to be erected.
Due to unforeseen circumstances, the works to the sewer connection in the highway will not be going ahead next week, but have been rescheduled for week commencing 12th August. Letters to residents surrounding the site will be posted out shortly explaining this.