This week the bricklayers have started with the brickwork to the perimeter of the building. Works internally are continuing at a rate of knots with the M&E teams working their way around the flats, the plumbers are now on the ground floor 1st fixing their final flat whilst the electricians are not too far behind them in the last of the four flats on the first floor. Meanwhile on the second floor the ply to the kitchens and bathrooms is complete enabling the partition team to start closing up the walls and ceilings. The metal work to the ceilings and the boarding to the reveals is underway.