Friday, 11 October 2013

Busy week again on site at Brown Royd. Brick work is all but complete, the rendering to the block work panels has been done this week, rain water pipes, gas pipes and mastic sealant have all been completed towards the back end of the week to enable the scaffolders to come to site next week and start dismantling the scaffold. Internally plumbing and electrical works are complete to the first and second floor flats.  The joiner is also now in the ground floor flats with two of the kitchens already installed and the second fixing has started. Decorations to the second floor are finished so they are now concentrating their efforts on the first floor.

 