The final few
sections of the scaffold have been removed so everybody can see the building in
all its glory, it certainly does stand well and fits in with the surrounding
area. The works to the
flats are continuing with the pre-finish items such as the doors in the flats
being fitted. Externally the
ground workers have joined the team back on site to start with the levelling up
of the perimeter, a trench has been excavated for the gas supply to the flats. We have set flags on
edge to the top elevation separating the site from the land above the site to
act as a retainer as there is a step in the ground. The base for the
cycle store has been poured so that this area can be
flagged. The communal areas
are now being skimmed so that the plywood flooring can be fitted early next
week.