Friday, 4 October 2013

Last week was Wates Community Day and the guys on site all mucked in to clear the footpath just outside the site. We cleared all the over grown shrubbery, made the ground level and laid some stone and compacted it with a roller to make it a lot more suitable for locals to use.

The job itself is coming on leaps and bounds, the block work for the rendered panels is complete and brick work isn't too far behind, another good week next week and it shouldn't be too far away.

Internally electrical works to the communal area are ongoing.

Joinery second fix is progressing well throughout the first floor.

The tiler has been back on site this week to carry on with the kitchen and bathroom areas to the first floor.

Decorations have commenced to the second with the decorators concentrating their efforts on the flats bringing them to a finish before moving down to the first floor.